Preparation and brief project stage
NB the RIBA Plan of Work 2020 renamed this stage 'Preparation and briefing'.
The process for completing the design and construction of a building is often divided into stages. This can be helpful in establishing milestones for the submission of progress reports, the preparation of information for approval, client gateways, and for making payments.
However, there is a great deal of ambiguity between the naming of stages by different organisations and the definition of what individual stages actually include (see comparison of work stages), and so it is important that appointment documents make it clear specifically what activities fall within which stage, and what level of detail is required.
‘Preparation and brief’ is a new phrase coined by the Royal Institute of British Architects (RIBA) for their 2013 Plan of Work. This plan comprises eight work stages, and its new terminology, stage referencing system and lack of detail have generated some criticism.
- 0 - Strategic definition.
- 1 - Preparation and brief.
- 2 - Concept design.
- 3 - Developed design.
- 4 - Technical design.
- 5 - Construction.
- 6 - Handover and close out.
- 7 - In use.
The preparation and brief stage involves:
- Developing an initial project brief. This may include; considering feedback from previous projects, defining overall spatial requirements, carrying out surveys and quantifying the budget.
- Carrying out feasibility studies.
- Undertaking a project risk assessment, including; planning risks, programme and procurement strategy.
- Assembling the project team and defining their roles and responsibilities.
This preparatory work enables the design process to begin in the next stage ‘concept design’.
The RIBA suggest that this new stage 1 merges the ‘residual’ tasks from the former Stage A ‘Appraisal’ and Stage B ‘Design Brief’.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Briefing documents.
- Comparison of work stages.
- Designing Buildings Wiki Project plans.
- Design responsibility matrix.
- Feasibility studies.
- Project brief.
- RIBA Plan of Work.
- Risk assessment.
[edit] External references
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Building Safety Newsletter from MHCLG.
An extraordinary record of steel engineering worldwide.
Households living near new pylons to save on bills.
ECA warns growth must not outpace grid capacity or skills.
The role of the client and decision making
CIOB response to built environment professions call for evidence.
Construction's sustainability reporting revolution
Tracking upfront embodied carbon with digital tools.
ECA welcomes procurement reforms
Public spending must back British jobs and skills.
Campaigning for Edinburgh: the Cockburn Association 1875-2049
The role of the civic voice in protecting character. Book review.
CIOB photography competition is open for entries.
ECA Edmundson apprentice of the year award
Finalists announced.
Major new study exposes serious knowledge gaps.
Generating energy from internal light as well as sunshine.